Comparing capacity factor across turbine generations on a repowering shortlist

A portfolio manager building a repowering shortlist usually starts with the number that's easiest to pull: capacity factor, site by site, straight out of the asset register. It feels like a ranking. It isn't one, not until you account for what generation of turbine produced that number.
A site commissioned in 2005 running Vestas V47s at 50m hub height and a site commissioned in 2015 running V90s at 80m can show similar capacity factors on paper while sitting on very different wind resources, and very different headroom for a bigger machine. The old site might look like a mediocre performer when really it's a good wind site stuck on a small rotor. That's the site you want near the top of the shortlist. Raw capacity factor alone will bury it under newer assets that have less room left to improve.
Why raw capacity factor misleads you across generations
Capacity factor is a ratio of actual output to nameplate output over time. It moves with three things that have nothing to do with how good the wind resource is: rated capacity, rotor diameter, and hub height. A 1.5 MW turbine with a 70m rotor at 65m hub height and a 4 MW turbine with a 150m rotor at 100m hub height will post different capacity factors on identical wind, because the swept area and the shear profile they're each exposed to are different. Comparing those two numbers directly tells you about the machines, not the site.
What you actually want to know, for ranking purposes, is: given the wind this site has shown over its operating history, what would a current-generation turbine class do here, and how much of that gap is real uplift versus just catching up to what a modern machine would get anywhere.
Normalizing old vs new turbine output before you rank
A few steps that get you closer to comparing old and new turbines on equal terms, machine for machine:
- Pin down the actual turbine model per site, not what's in the original spec sheet. Blade upgrades, uprates, and gearbox swaps change the effective power curve, and asset registers lag these changes more often than people expect.
- Treat long-term operating data as your resource proxy. Years of actual generation, corrected for downtime and curtailment, is a better read on the wind at hub height than a single resource assessment from the original feasibility study.
- Run a candidate repower turbine's published power curve against that same resource class. This gives you a projected capacity factor for the new machine, not a generic industry-average uplift figure.
- Subtract the two to get a yield uplift estimate per site, and keep it as a range, not a point figure, until a project team does a proper energy assessment.
- Weight that uplift against how hard the consent will actually be. A site with a strong uplift number but a blade-tip height increase that trips a new aviation lighting requirement, or sits inside a tightened ecology buffer, may rank below a site with a smaller uplift and a cleaner planning path.
That last step is where most shortlists go wrong. Teams rank by projected uplift and then discover the consent friction only after committing engineering time to the top two or three sites. Ranking on uplift and consent difficulty together, from the start, is the point of the exercise.
Getting step one right, the confirmed turbine model and count on site, is usually the slowest part of this process when it's done by cross-checking a model database against old site photos and maintenance logs by hand. Repowering Candidates ages a fleet against one annual VHR pass instead, so the model-confirmation step that feeds the capacity factor comparison doesn't start from a guess.
If you're already building a shortlist this quarter, it's worth seeing which of your sites come out ranked differently once age and consent difficulty are in the picture together.